In this newsletter issue:

Wastewater Treatment Plant Pump Suction Isolation Gates | Metro Vancouver

  • Concept generation and detailed design of five gates to isolate influent pumps
  • 3D scanning and modelling
  • Full tender package and capital cost estimates

Nootka Island Derrick Landing and Float Reconstruction| Department of Fisheries, Oceans, and the Canadian Coast Guard

  • Detailed design of piles, pile guides, landing platform, concrete abutment, and a lifting beam
  • Design optimization to avoid environmentally-sensitive areas
  • Prefabricated designs to minimize construction time

3D Modelling Technology | Featured CWA Service

  • 3D scanning, 3D modelling, finite element analysis, discrete element method modelling, and computational fluid dynamics
  • Greenfield sites and brownfield sites